Male’ Water and Sewerage Company (MWSC) has begun work on the water and sanitation project in Sh. Goidhoo.
MWSC said on Tuesday that the company is currently engaged in constructing the facility needed to house the water plant, and that pipes and other material needed for the project have been transported to Goidhoo.
The water project in Goidhoo involves establishing a 12.07-kilometer main water pipeline network, construction of an RO facility, installation of two RO plants, and three water tanks to store water.
Additional work includes installation of water meters in households, providing water connections, and supplying clean and safe drinking water.
The sanitation project, meanwhile, involves establishing a 7.30-kilometer main sanitation network, a 1.48-kilometer pump line, construction of an administrative building, three pump stations and one sea outflow.
Additional work includes establishing junctions in households, providing sanitation connections, and providing sanitation services to households.
Goidhoo water and sanitation project was contracted to MWSC by Planning, Housing and Infrastructure Ministry for MVR 86 million.
The company is required to complete the project within 540 days.