The Ministry of Infrastructure, Housing and Urban Development says 72.17 percent of the Thilamale' Bridge project has now been completed, with major structural components advancing steadily. According to the ministry, work is ongoing to cast and install the segments required for the bridge deck. Of the 1,222 segments needed, 86 percent have been cast, while around 60 percent have already been