Ministry of Housing and Infrastructure has said that the authority had started investigating the cracks on the piazza – a marble floor prayer area - outside Islamic Center.
Marble was placed on a 4,200 square meter area outside Islamic Center for Ramadan.
The USD 1.14 million project was completed within 16 days.
The project was funded through non-reimbursable financial aid by Chinese government.
The marble used was also donated by the Chinese government.
However, the 20,000-people capacity marble floor showed cracks after a month of use.
Housing Ministry announced through their official Twitter account on Sunday that they are investigating the cracks, and would take necessary steps to repair the damage.
The damages at the pattern area of Islamic Centre Piazza are being investigated and necessary action will be taken. @MMuizzu
— housing.gov.mv (@HousingGovMv) July 10, 2016