Ameen Construction assigned task of constructing building for RO Plant

Ameen Construction was awarded the task of constructing a building for a Reverse Osmosis Plant in Male’.

Male Water and Sewerage Company (MWSC) awarded the job of bringing a new RO Plant to Male to a Japanese company in 2015. The Plant will be brought to Male’ this year. And Ameen

Construction has been awarded the task of constructing a building for it.

The agreement was signed in a ceremony held Wednesday afternoon on behalf of MWSC by Managing Director of the company, Ibrahim Fazul; and on behalf of Ameen Construction by Managing Director of the company, Abdulla Mohamed.

Fazul said that the Plant would be brought to Male’ on May, and that the Plant would be installed and fully functional by June.

Ameen Construction is required to complete the MVR 3.8 million project within 120 days.

Fazul said that the Plant would be kept in the MWSC land to the west of Fuel Supply Petrol Shed.